Bridge P-17337

55e avenue, Lachine

Project Summary

Cost
16 169 000$
Execution period
2020-2021
Type of contract
Contract
Client
MTQ

Présentation

The project is classified as a complex structure and is defined by the demolition and the reconstruction of an overpass of Highway 520 above the 55th avenue. The main challenges of the project are the maintenance and management of movement, the installation of temporary holding walls, the formwork and setting up of the structural concrete.

Similar Projects

  1. P17310 & P17304 Bridges

    Chemin Gowan, Hinchinbrokke
  2. Bridges 81-05543 & 81-05544

    Boulevard de l'île-des-soeurs, Verdun

Make a Difference Every Day

Feeling that our thoughts, our ideas, our solutions make a difference is stimulating and energizing, isn’t it? We feel like going beyond limits, giving more, and reinventing ourselves constantly. At Tisseur, we create projects for the future, and a future jewel of Quebec. Does this vision appeal to you? Embark on this great adventure!

Find out more