Lachine Canal Wall - Basin no. 3

Rue Saint-Patrick, Montréal

Project Summary

Cost
3 800 000$
Execution period
2019-2020
Type of contract
Contract
Client
Canada Parks

Présentation

The project consists of the rehabilitation of the walls of the Lachine Canal including the management of the contaminated soil, the formwork and the concrete for the reconstruction of the walls and the development of a new bike path.

Similar Projects

  1. Lachine Canal Wall, Sectors H.4 & 12

    Rue Saint-Patrick, Montréal
  2. Lachine Canal Wall, Sections 18e to 21e

    Boul. Saint-Joseph, Montréal
  3. Wall of the Old Brewery

    Boul. Saint-Joseph, Montréal

Make a Difference Every Day

Feeling that our thoughts, our ideas, our solutions make a difference is stimulating and energizing, isn’t it? We feel like going beyond limits, giving more, and reinventing ourselves constantly. At Tisseur, we create projects for the future, and a future jewel of Quebec. Does this vision appeal to you? Embark on this great adventure!